Client: - ( Abu Dhabi Municipality )
Main Contractor: - Ampere Electrical Contracting Est
Project Detail
Material Used:-
Main Contractor: - Ampere Electrical Contracting Est
Project Detail
- Visited the site, did the survey and checked out the requirements for the number of motion sensors required for the exact solution
- Fabrication of the control pannel
Material Used:-
- GI conduit laying for the control cabling for motion sensors.
- install the motion sensor of 220 volt supply (From Sens Light)
- Siemens PLC Logo soft confort of latest version 6.1.
- write the software programming the loaded on the logo( intial problem was coming of tranfer of program to logo but we found our sofware was of older version and logo was latest so purchased the latest software version also
- contactors of 25Ampere of 220 volt coil supply of Federal Electric and Siemens installed.
- Siemens Contractor are good for frequest jerks
- Each Floor control panel made seperatly and installed on each floor level.
- Light circuit fault were cleared also,
- Due to non electronic choke of lights , so many lights were found faulty due to frequest ON OFF
- Note:- Initially Project was awarded to GISCO, but because GISCO maintenance contract was finished on December 2010 as due their non availabilty and there no interest in the project so Municipality has awarded the same project to Ampere Electrical Contracting on the same agreed price.